Health Security Se National Security Cess Rules, 2026
Chapter V - CESS ABATEMENT AND COMPUTATION
Rule 15 - Conditions for abatement
15. Conditions for abatement.-
(1) The abatement under sub-section (7) of section 5 of the Act shall be available when the following conditions are satisfied, namely:-
(a) the registered person intimates the proper officer at least three working days before the non-operation of an installed machine or manual process unit for any continuous period of fifteen days or more, requesting the sealing of the machine or closure of manual process unit, as the case may be;
(b) the packing machine or manual process unit is sealed by the proper officer within three working days from the date of receipt of intimation in such a manner that it cannot be operated;
(c) no manufacturing activity for the specified goods is undertaken on the said machine or by the manual process unit, as the case may be, during the period of sealing.
(2) Any registered person eligible for abatement under sub-rule (1), shall claim such abatement by submitting an application to the proper officer on or before the 20th day of the month succeeding the period for which the abatement is claimed.
(3) The proper officer shall, upon verification of the claim submitted under sub-rule (2), issue an order, within fifteen days of the submission of such application, allowing the abatement of the cess liability for each month covered by the period of non-operation of the machines or manual unit, which shall be adjusted against the cess liability payable for the month immediately following the month in which such order is issued:
Provided that no order rejecting the claim of abatement, either in whole or in part, shall be passed unless the registered person has been given a reasonable opportunity of being heard.
Explanation.- For the purposes of this rule, “installed machine” refers to an operational machine that has become nonoperative during the period of abatement
Act
-
THE HEALTH SECURITY SE NATIONAL SECURITY CESS ACT, 2025