Service Tax – Cestat Chennai: Encashment of performance Guarantee/ Bank Guarantee and that collected/ retained as liquidated damages for non-performance and failure to comply with the agreed obligation are not a consideration for provision of service, cannot be subjected to Service tax – Appeal allowed [Order attached]
Your free trial / membership plan is expired.
Kindly subscribe to get complete access to indirect tax updates and issue wise cases
Why subscribe to us ?
Get complete access to news updates and download copy of case laws/ notification/ circular etc.
Be a part of our WhatsApp group and read real time indirect tax updates
Access to ready case laws of General Issues and Industry Wide Issues under GST
Access to relevant provisions of law / circular in respect to the issues, along with trail of their amendments
Write your GST query to us for evaluation
Subscription Charges:*
Indirect tax updates -
6 months @299 / 1 Year @499 only
Indirect tax updates + Issue wise cases -
6 months @1199 / 1 Year @1999 only
*Plus applicable GST
Admin
19-Sep-2023 10:07:15
Order Date – 12 September 2023
Parties: Chennai Metro Rail Ltd. Vs Commissioner of GST & Central Excise
Facts –
- The Appellant, Chennai Metro Rail Ltd. (CMRL), is a joint venture between the Government of India and the Government of Tamil Nadu that builds and operates Chennai Metro.
- A Show Cause Notice dated 29.9.20218 was issued to demand the service tax received through encashment of performance Guarantee / Bank Guarantee and towards collected/ retained as liquidated damages during the period along with interest and for imposition of penalties under various sections of Finance Act, 1994.
- The demand was dropped with respect to the encashment of performance Guarantee / Bank Guarantee and demand along with interest and penalty was confirmed on liquidated damages. Being aggrieved both the appellant and the department filed appeals.
Issue –
- Whether the demand of service tax on liquidated damages are valid?
Order -
- The Tribunal observed that the issue is no longer res intigra and has been clarified by the CBIC itself as per the Circular No. 214/1/2023-Service Tax dated 28-02-2023 which clarified that when one party agrees to refrain from an act, or to tolerate an act or a situation, or to do an act, are the activities where the agreement specifically refers to such an activity and there is a flow of consideration for this activity.
- Revenue has not pointed out any such contractual arrangement which is an independent arrangement in its own right to receives damages by tolerating breach of contract. The amounts retained towards liquidated damages and also invoked as bank guarantee are not a consideration for tolerating breach of contract. Any amount, which is not a consideration for provision of service, cannot be subjected to service tax.
- A demand for service tax on the monies received through encashment of performance Guarantee / Bank Guarantee and that collected/ retained as liquidated damages for non-performance and failure to comply with the agreed obligation by various contractors / sub-contractors, hence fails. the demands for duty along with interest made and the penalties imposed by the impugned order are Set aside. The appeal filed by the appellant succeeds and is allowed.
Related Post
- 57th GST Council recommendations: Reforms to simplify compli...
- GST - Government has extended the last date for filing GSTAT...
- GSTN is strengthening e-Way Bill ecosystem by making “Ship...
- GSTAT has extended relaxed and simplified appeal filing proc...
- GST News: Due to GST Portal Glitch, Govt Likely to Extend Ma... View All
Your free trial/ membership plan has expired. Kindly subscribe to get complete access of tax news updates.
Why subscribe to us ?
Get complete access to news updates
Access to the Order Copy of the case law/ Notification/ Circular etc
Be a part of our Whatsapp group and read real time tax updates
Access to ready case laws/ circulars on general and industry-wide issues under GST
Submit your GST issues to us for evaluation